Installation of temporary raking props, Ground level slab removal, cropping of existing perimeter RC frame wall structures.
Our current major project on Dover Demolition for the past year. We are subcontracted by Coniston to complete the full demolition of the old Science block at The King’s School Canterbury within the Cathedral grounds.
Phase 2 of the project began in December 2019 the team installed raking props as per the engineering drawings before the ground level slab could be mechanically removed and the existing RC frame perimeter basement wall structures could be cropped.