Hoarding, Soft Strip, roof removal & demolishing existing RC structure to slab level.
Our current major project on Dover Demolition for the past year. We are subcontracted by Coniston to complete the full demolition of the old Science block at The King’s School Canterbury within the Cathedral grounds.
In the first phase beginning June 2019 we erected a hoarding tunnel at the front of the school to enable the students safe access to the school whilst the works were being carried out.
The demolition team completed a soft-strip of the block, removing all interior fixtures and fixings, floors, ceilings and walls. They also completed a full roof removal including tiles and roof trusses.
During this phase the team also completed RND installation for temporary bank infill and a full mechanical demolition of the RC frame down to slab level.